With just one week of spring underway, we have a lot to look forward to at the Village at Ocean’s End as we head through spring and into summer.
Unit 6 (photos and floor plans here) is 95% complete and is a beautiful summer getaway.
Unit 5 has most of its siding and will be completely sheetrocked next week!
Unit 8 is coming along as well and now has walls inside and will soon have a shingled roof.
We will be breaking ground on Unit 3 next Monday and will have another house completed this summer.
Also on the development’s agenda this spring is the continuation of the sidewalk. It has been a mild winter, and hopefully that means a long warm summer too! We can’t wait to see all the visitors start pouring in over the next few weeks. Remember, if you are here this spring or summer, to contact our realtor and schedule a tour of the Village at Ocean’s End.
Unit 6 (photos and floor plans here) is 95% complete and is a beautiful summer getaway.
Unit 5 has most of its siding and will be completely sheetrocked next week!
Unit 8 is coming along as well and now has walls inside and will soon have a shingled roof.
We will be breaking ground on Unit 3 next Monday and will have another house completed this summer.
Also on the development’s agenda this spring is the continuation of the sidewalk. It has been a mild winter, and hopefully that means a long warm summer too! We can’t wait to see all the visitors start pouring in over the next few weeks. Remember, if you are here this spring or summer, to contact our realtor and schedule a tour of the Village at Ocean’s End.